Prevention and Healthy Lifestyles must Go Hand in Hand with Disease Treatment : Jadhav (See 'Corp Brief') Ministry of Textiles to organise IIHT SUTRA 2026 (See 'Corp Brief') A&C - Award is patently illegal and liable to be set aside if it ignores vital evidence, applies circular logic, or blocks party from presenting its case: HC (See 'Legal Desk') In a first, 'Vande Mataram' to be sung from ramparts of historic Red Fort (See 'Corp Brief') National Handloom Designers' Conclave showcases Design-Led Innovation (See 'Corp Brief') PBPT - Routing of funds through company to appellant squarely attracts Section 2(9)(A) of the Act as property stood in name of benamidar while consideration emanated from beneficial owner: SAFEMA Tribunal (See 'Legal Desk') PM-YASASVI Scheme implementation in Maharashtra reviewed Regularly: Govt (See 'Corp Brief') MoS calls for greater Private Sector Participation in Biotechnology Ecosystem (See 'Corp Brief') IBC - Right of Personal Guarantor to invoke insolvency provisions of Sec 94 of IBC is statutory right that cannot be extinguished merely because Financial Creditor has initiated recovery proceedings under SARFAESI: NCLT (See 'Legal Desk') Empowering Nari Shakti: 1 crore houses allotted to women (See 'Corp Brief') MoS dedicates to nation first-of-its-kind 'Eco-Educational Hub' (See 'Corp Brief') NI Act - Moratorium protects corporate debtor in respect of insolvency proceedings, but does not grant immunity to natural persons from criminal liability already incurred on account of cheque dishonour: HC (See 'Legal Desk') XI BRICS Culture Ministers' meeting concludes in Bhopal (See 'Corp Brief') A&C - If prima facie arbitration agreement exists and non-signatories have shown conduct aligning with contract, referral court should allow arbitrator to finalize list of parties based on detailed evidence: HC (See 'Legal Desk') Railways approves introduction of Daily Itarsi-Madan Mahal Passenger Service (See 'Corp Brief') A&C - Arbitral award is patently illegal if it is rendered in summary manner without allowing parties to lead evidence or be heard on critical pleadings: HC (See 'Legal Desk') 13th BRICS Education Ministers' meeting concludes with Declaration (See 'Corp Brief') IEPFA organises Stakeholder Engagement with Nodal Officers of Companies on Portal 2.0 (See 'Corp Brief') SARFAESI - Any tenancy created after issuance of notice u/s 13(2) without prior written consent of secured creditor, is void ab initio: HC National Handloom Day celebrates Tribal Weaves of India (See 'Corp Brief') SECL leads India in Scientific Mine Closure, Transforming abandoned Mines (See 'Corp Brief') IBC - RBI prudential norms stopping banks from recognising interest income on NPA accounts do not wipe out borrower's obligation to accrue & recognise interest expense in its own financial statements: NCLAT (See 'Legal Desk') Sowa-Rigpa must emerge as Globally Recognised Evidence-Based Healthcare System: Jadhav (See 'Corp Brief') Insurance Division, DFS secures 3rd Rank in Group A Category of Grievance Redressal (See 'Corp Brief') IPR - Registration of defendant's trademark does not bar passing off action where plaintiff establishes prior goodwill, misrepresentation and likely damage: HC (See 'Legal Desk') Tete-a-tete around AI in banking sector often begins with algorithms (See CORP EINSICHT)

Nepalese PM triggers last blast of Head Race Tunnel of Arun-3 Hydro Electric Project

Published: Jun 06, 2024

By TIOLCorplaws News Service

NEW DELHI, JUNE 06, 2024: PRIME Minister of Nepal Pushpa Kamal Dahal 'Prachanda' triggered the last blast to mark the completion of heading excavation for the 11.8 km long Head Race Tunnel of 900 MW Arun- 3 Hydro Electric Project in Sankhuwasabha District of Nepal. Arun - 3 Hydro Electric Project is being executed by SJVN Arun-3 Power Development Company Pvt. Ltd. (SAPDC), a fully owned subsidiary of SJVN. SAPDC is a significant collaboration between SJVN and the Government of Nepal, which aims to enhance regional energy security and boost economic development through sustainable hydropower generation in Arun River Basin.

Minister of Energy, Water Resources and Irrigation of Nepal Shakti Bahadur Basnet; Health Minister, Province 1 of Nepal Rajender Karki; India's Ambassador to Nepal Naveen Srivastava; Chairperson & Managing Director, SJVN, Sushil Sharma; CEO, Investment Board of Nepal. Sushil Bhatta; CEO, SAPDC, Arun Dhiman; Executive Director, SJVN, Rakesh Sehgal ; and other officials of Government of Nepal and local authorities were present at the tunnel breakthrough ceremony.

Addressing the gathering, the Prime Minister of Nepal said that this breakthrough brings us closer to the goal of providing clean, renewable energy and in contributing to the sustainable development of the region. He expressed his appreciation for the ongoing efforts and reaffirmed the commitment of the Government of Nepal to facilitate the timely completion of Arun - 3 Hydro Electric Project.

India's Ambassador to Nepal Naveen Srivastava recalled in his address that the Prime Minister of India Narendra Modi and his Nepali counterpart Pushpa Kamal Dahal 'Prachanda' had agreed last year, to the long-term power trade agreement for the import of electricity from Nepal. He said that completion of export-oriented 900 MW Arun 3 Hydro Electric Project will be a major milestone for this.

CMD, SJVN, Sushil Sharma apprised the Prime Minister of Nepal that the successful breakthrough of the Head Race Tunnel marks a significant milestone in the construction of the 900 MW Arun-3 Hydro Electric Project. He added that the successful completion of the Head Race Tunnel is a monumental achievement in the journey to harness the hydropower potential of the Arun River.

The CMD briefed the Prime Minister about the progress of the project and the associated 217 km. long transmission line. He informed that more than 74% of the project works have been completed and that the remaining works are going on in full swing. He added that Arun- 3 Hydro Electric Project will start generating electricity by next year and that it has the potential to generate 3,924 million units of electricity every year.

The CMD said: "We are grateful for the unwavering support from the Government of Nepal, local authorities, and the community. This project symbolizes the strong partnership between India and Nepal in the energy sector and our collective efforts to achieve energy security and environmental sustainability."

During his visit to Nepal, CMD, SJVN also met with Chief Secretary of Nepal Dr. Baikuntha Aryal and Home Secretary of Nepal Eaknarayan Aryal and discussed various issues related to development of hydroelectric projects in Arun Valley in Nepal.

Currently, SJVN is executing 2,200 MW of three Hydroelectric Projects on Arun River basin in Nepal.