Govt reviews Use of Steel from Ship Recycling to Boost Steel Manufacturing (See 'Corp Brief') Inaugural PDUNASS–GNLU Executive Program on Labour Law concludes at Gandhinagar (See 'Corp Brief') Workshop held to empower CPSEs for Global and Domestic Debt Markets (See 'Corp Brief') BHASHINI, Current AI and Kalpa Impact showcase Open-Source AI Solutions for India (See 'Corp Brief') Manohar Lal participates in G20 Energy Abundance Ministerial Meeting (See 'Corp Brief') PM Vishwakarma: 30 Lakh Artisans Registered under Scheme (See 'Corp Brief') A&C Act - Question whether particular claim is covered by, or falls outside excepted matters clause of works contract is matter squarely within competence of Arbitral Tribunal u/s 16 of Arbitration and Conciliation Act: SC (See 'Legal Desk') Scindia releases commemorative Postage Stamp in Memory of Sant Malukdas Ji (See 'Corp Brief') Khadse reviews sports ecosystem in Mizoram; visits SAI Aizawl (See 'Corp Brief') NTPC WR-I Hqs gears up to host Mumbai Regional Round of NTPC Electron Quiz (See 'Corp Brief') Competition Act - Regulatory decisions taken in exercise of statutory powers not subject to review by CCI; authority concerned is not amenable to scrutiny u/s 4 of Competition Act: CCI (See 'Legal Desk') Conventional to Smart Mining: Technology Transformation of Coal India Ltd (See 'Corp Brief') NSTFDC joins hands with HPCL for Computer Lab-cum-Smart Classroom in 29 Eklavya Schools (See 'Corp Brief') Repair before Replace, Reuse before Discard, Recover before Waste, says Yadav (See 'Corp Brief') SEBI - Penalty order under SEBI (PFUTP) Regulations unsustainable where foundational findings regarding volume of manually deleted orders & manipulative intent are perverse & contrary to the record: SAT (See 'Legal Desk') Varuna Elevated Corridor: Balancing Heritage, Mobility and Growth in Varanasi (See 'Corp Brief') Commercial Coal Mine Auctions: Powering Aatmanirbhar Bharat Through Transparency (See 'Corp Brief') Capital Market - Release of escrow amount maintained for buyback does not bar separate inquiry into alleged fraud under PFUTP Regulations: SC (See 'Legal Desk') Postal Employee Organisations hail the Government for 'reinventing' India Post (See 'Corp Brief') DFS wins First Prize under 'Rajbhasha Kirti' for 2025-26 (See 'Corp Brief') IBC - Where a plausible dispute requiring further investigation exists & the defence is not patently feeble, a petition u/s 9 cannot be admitted: NCLT (See 'Legal Desk') India world's largest Vaccine producer and global supplier by volume: MoS (See 'Corp Brief') Mizoram's Railway Lifeline completes One Year of Success (See 'Corp Brief') PBPT - Transfer of funds by beneficial owner to purchase properties in names of relatives without demonstrable loan agreements or independent source of income is classic benami transaction under the Act: SAFEMA Tribunal (See 'Legal Desk') Expanding coal production and infrastructure while widening opportunities in Central India (See 'Corp Brief') Cochin Shipyard Ltd and Drydocks World Form JV To strengthen India's Ship Repair Industry (See 'Corp Brief') FEMA - Financial difficulties do not excuse non-compliance with mandatory FEMA requirements - Funds received via FDI cannot be utilised or diverted for purposes other than those for which they were received: SAFEMA Tribunal (See 'Legal Desk') Next Subscription Economy may arrive with Telecos monthly bills (See CORP EINSICHT)

Nepalese PM triggers last blast of Head Race Tunnel of Arun-3 Hydro Electric Project

Published: Jun 06, 2024

By TIOLCorplaws News Service

NEW DELHI, JUNE 06, 2024: PRIME Minister of Nepal Pushpa Kamal Dahal 'Prachanda' triggered the last blast to mark the completion of heading excavation for the 11.8 km long Head Race Tunnel of 900 MW Arun- 3 Hydro Electric Project in Sankhuwasabha District of Nepal. Arun - 3 Hydro Electric Project is being executed by SJVN Arun-3 Power Development Company Pvt. Ltd. (SAPDC), a fully owned subsidiary of SJVN. SAPDC is a significant collaboration between SJVN and the Government of Nepal, which aims to enhance regional energy security and boost economic development through sustainable hydropower generation in Arun River Basin.

Minister of Energy, Water Resources and Irrigation of Nepal Shakti Bahadur Basnet; Health Minister, Province 1 of Nepal Rajender Karki; India's Ambassador to Nepal Naveen Srivastava; Chairperson & Managing Director, SJVN, Sushil Sharma; CEO, Investment Board of Nepal. Sushil Bhatta; CEO, SAPDC, Arun Dhiman; Executive Director, SJVN, Rakesh Sehgal ; and other officials of Government of Nepal and local authorities were present at the tunnel breakthrough ceremony.

Addressing the gathering, the Prime Minister of Nepal said that this breakthrough brings us closer to the goal of providing clean, renewable energy and in contributing to the sustainable development of the region. He expressed his appreciation for the ongoing efforts and reaffirmed the commitment of the Government of Nepal to facilitate the timely completion of Arun - 3 Hydro Electric Project.

India's Ambassador to Nepal Naveen Srivastava recalled in his address that the Prime Minister of India Narendra Modi and his Nepali counterpart Pushpa Kamal Dahal 'Prachanda' had agreed last year, to the long-term power trade agreement for the import of electricity from Nepal. He said that completion of export-oriented 900 MW Arun 3 Hydro Electric Project will be a major milestone for this.

CMD, SJVN, Sushil Sharma apprised the Prime Minister of Nepal that the successful breakthrough of the Head Race Tunnel marks a significant milestone in the construction of the 900 MW Arun-3 Hydro Electric Project. He added that the successful completion of the Head Race Tunnel is a monumental achievement in the journey to harness the hydropower potential of the Arun River.

The CMD briefed the Prime Minister about the progress of the project and the associated 217 km. long transmission line. He informed that more than 74% of the project works have been completed and that the remaining works are going on in full swing. He added that Arun- 3 Hydro Electric Project will start generating electricity by next year and that it has the potential to generate 3,924 million units of electricity every year.

The CMD said: "We are grateful for the unwavering support from the Government of Nepal, local authorities, and the community. This project symbolizes the strong partnership between India and Nepal in the energy sector and our collective efforts to achieve energy security and environmental sustainability."

During his visit to Nepal, CMD, SJVN also met with Chief Secretary of Nepal Dr. Baikuntha Aryal and Home Secretary of Nepal Eaknarayan Aryal and discussed various issues related to development of hydroelectric projects in Arun Valley in Nepal.

Currently, SJVN is executing 2,200 MW of three Hydroelectric Projects on Arun River basin in Nepal.