Coal India advances Technology-led Diversification Across Energy & Minerals (See 'Corp Brief') Digital India RISC-V Grand Challenge under C2S Programme awarded to 3 teams (See 'Corp Brief') IBC - Arrangement of funds to enable corporate debtor to clear its liabilities, coupled with transfer of funds from cooperative bank loan account of applicant directly to bank, is not valid loan disbursement under IBC: NCLT (See 'Legal Desk') Vaishnaw highlights ISM 2.0, indigenous design, manufacturing, talent and India's emergence (See 'Corp Brief') SEBI - SEBI, acting as statutory market regulator, is duty-bound to issue a reasoned, speaking order when a decision carries serious civil consequences for acquirer, target company & investors: SAT (See 'Legal Desk') An unsuccessful 'success fee' litigation (See CORP EINSICHT) Centre commemorates World Patient Safety Day 2026 at NIHFW (See 'Corp Brief') BIMSTEC Energy Centre organises 5-Day Capacity Building Programme (See 'Corp Brief') Scindia inaugurates Renovated Guna Head Post Office in MP (See 'Corp Brief') SEBI - Where material on record discloses need for deeper scrutiny, re-appreciation, review or reconsideration of evidence, leave ought to be granted & the appeal should thereafter be decided on merits: HC (See 'Legal Desk') CCI nod for acquisition of equity of Great White Global by ISAF III Onshore Fund (See 'Corp Brief') From Ink and Ledger to Cloud and Cipher: The Bankers' Books Evidence Act, 2026 - A Critical Appraisal of India's Digital Evidentiary Revolution (See CORP EINSICHT) A&C Act - Question whether particular claim is covered by, or falls outside excepted matters clause of works contract is matter squarely within competence of Arbitral Tribunal u/s 16 of Arbitration and Conciliation Act: SC (See 'Legal Desk') CCI approves acquisition of addl share in Azure Power Global by OMERS Infra (See 'Corp Brief') Beneficiaries express confidence in government policies for e-mobility (See 'Corp Brief') Competition Act - Regulatory decisions taken in exercise of statutory powers not subject to review by CCI; authority concerned is not amenable to scrutiny u/s 4 of Competition Act: CCI (See 'Legal Desk') Semicon 2.0 mission to focus semiconductor design & fabrication; to create 1 lakh jobs (See 'Corp Brief') NLMC to host investor meets ahead of RINL land e-auction (See 'Corp Brief') SEBI - Penalty order under SEBI (PFUTP) Regulations unsustainable where foundational findings regarding volume of manually deleted orders & manipulative intent are perverse & contrary to the record: SAT (See 'Legal Desk') Govt reviews Use of Steel from Ship Recycling to Boost Steel Manufacturing (See 'Corp Brief') Inaugural PDUNASS–GNLU Executive Program on Labour Law concludes at Gandhinagar (See 'Corp Brief') Capital Market - Release of escrow amount maintained for buyback does not bar separate inquiry into alleged fraud under PFUTP Regulations: SC (See 'Legal Desk')

India's RE capacity registers 14.2% Year-on-Year growth

Published: Dec 12, 2024

By TIOLCorplaws News Service

NEW DELHI, DEC 12, 2024: MINISTRY of New and Renewable Energy (MNRE) has reported significant progress in India's renewable energy sector from November 2023 to November 2024. This progress underscores India's commitment to achieving its clean energy targets in line with the ‘Panchamrit' goals set by Prime Minister Narendra Modi.

Record Capacity Additions

As of November 2024, the total non-fossil fuel installed capacity has reached 213.70 GW, marking an impressive 14.2% increase from last year's 187.05 GW. Meanwhile, the total non-fossil fuel capacity, which includes both installed and pipeline projects, surged to 472.90 GW, a substantial 28.5% increase from the previous year's 368.15 GW.

During FY 24-25 a total of 14.94 GW of new RE capacity was added till November 2024, nearly doubling the 7.54 GW added during the same period in FY 23-24. In November 2024 alone, 2.3 GW of new capacity was added— marking a dramatic fourfold increase from the 566.06 MW added in November 2023.

Solar and Wind Power Experience Significant Growth

India's renewable energy sector has seen widespread growth across all major categories. Solar power continues to lead, with installed capacity rising from 72.31 GW in 2023 to 94.17 GW in 2024, a robust growth of 30.2%. Including pipeline projects, total solar capacity surged by 52.7%, reaching 261.15 GW in 2024, compared to 171.10 GW in 2023. Wind power also made notable contributions, with installed capacity rising from 44.56 GW in 2023 to 47.96 GW in 2024, reflecting a growth of 7.6%. Total wind capacity, including pipeline projects, increased by 17.4%, from 63.41 GW in 2023 to 74.44 GW in 2024.

Steady Contributions from Bioenergy, Hydro, and Nuclear Sectors

Bioenergy and hydroelectric projects also made steady contributions to the renewable energy mix. Bioenergy capacity rose from 10.84 GW in 2023 to 11.34 GW in 2024, reflecting a growth of 4.6%. Small hydro projects saw a slight increase, from

4.99 GW in 2023 to 5.08 GW in 2024, with total capacity, including pipeline projects, reaching 5.54 GW. Large hydroelectric projects grew incrementally, with installed capacity rising from 46.88 GW in 2023 to 46.97 GW in 2024, and total capacity, including pipeline projects, increasing to 67.02 GW from 64.85 GW in the previous year.

In nuclear energy, installed nuclear capacity grew from 7.48 GW in 2023 to 8.18 GW in 2024, while the total capacity, including pipeline projects, remained steady at  22.48GW.

These impressive figures underscore the Government of India's continued efforts to scale up renewable energy capacity and reduce dependence on fossil fuels. MNRE under Union Minister of New and Renewable Energy Pralhad Joshi has been taking various key initiatives reflecting India's dedication to fulfilling its climate commitments while strengthening energy security.