MoS announces Rs.720 Crore Quantum Fabrication facilities at IIT Bombay (See 'Corp Brief') India, Afghanistan to deepen cooperation in Textile Sector (See 'Corp Brief') MoS lauds Quantum sensing breakthroughs by IIT, inaugurates first Liquid Helium Cryogenic facility (See 'Corp Brief') Evidence-Based Ayurvedic Products are Future of Wellness: Jadhav (See 'Corp Brief') Hotel, Industry & farmers partnerships is Critical for mutual growth: Agri Secy (See 'Corp Brief') MeitY launches Cyber Security Innovation Challenge (See 'Corp Brief') India-Oman Joint Military Cooperation Committee meeting held in New Delhi (See 'Corp Brief') A&C - Once right to file written statement is closed, application under Section 8 of Arbitration and Conciliation Act seeking reference to arbitration is not maintainable: HC (See 'Legal Desk') 'Workers are the miners of nation-building': Sonowal (See 'Corp Brief') India strengthens Textile and Sericulture Cooperation with Georgia (See 'Corp Brief') J&K to host launch of First Limestone Block Auction Roadshow (See 'Corp Brief') Indian Railways crosses 1 Billion Tonne Freight Loading in FY 25-26 (See 'Corp Brief') FEMA - Indian currency falls within scope of 'property' u/s 63 of FERA, empowering authorities to confiscate it when used in contravention of law: HC (See 'Legal Desk') IICA, DGR conclude Certification Program for senior Defence Officers (See 'Corp Brief') Op Drishti: Over 400 surgeries performed at Northern Command, J&K (See 'Corp Brief') ILO welcomes India's Labour Codes (See 'Corp Brief') Limitation Act - provisions of Limitation Act cannot be applied beneficially in favor of a petitioner who demonstrates mala fide intentions, including tampering with official documents: HC (See 'Legal Desk') PMLA - Pre-arrest protection would undermine integrity of ongoing investigation, and anticipatory bail in such cases should be granted sparingly: HC (See 'Legal Desk') RTI/SEBI - Refusal to disclose certain information justified, where details sought for pertains to commercial interests of third parties & received by SEBI in fiduciary capacity during its regulatory functions & disclosure of which could harm competitive position of relevant entities - YES: SEBI (See 'Legal Desk') Misc - When election process was initiated by notifying election and subsequently commenced, writ petition is not maintainable against it without exhausting alternate remedy: HC (See 'Legal Desk') PMLA - Question of substitution of attached property by way of any cash deposit or fixed deposit does not arise, if said property directly/indirectly acquired are attached, but not attached as value thereof: SAFEMA (See 'Legal Desk') Government intervention and Corporate governance (See CORP EINSICHT)

Minister lays foundation stone of two projects of CCL

Published: Oct 08, 2024

By TIOLCorplaws News Service

NEW DELHI, OCT 08, 2024: UNION Minister of State for Coal and Mines Satish Chandra Dubey yesterday laid the foundation stone of Karo Coal Handling Plant and Konar Coal Handling Plant in Bokaro and Kargali area of CCL. The capacity of these two projects is 7 million tonnes per annum and 5 million tonnes per annum respectively. Member of Parliament, Giridih, Chandra Prakash Chaudhary, MLA, Bermo, Kumar Jayamangal (Anoop Singh), Chairman of Coal India Limited, PM Prasad, CMD, CCL Nilendu Kumar Singh, senior officers of CCL, representatives of workers' union and other stakeholders were present on the occasion. Minister Dubey also planted saplings during the foundation stone laying ceremony of Konar Project under the campaign "Ek Ped Maa Ke Naam".

Karo and Konar coal handling plants will prove to be an important step in the direction of First Mile Rail Connectivity, under which arrangements will be made to take the coal produced from the coal mines to the nearest railway circuit, from where it will be transported to thermal power plants and other consumers across the country. Currently, coal from these mines is brought to the railway siding by road.

Konar Coal Handling Plant : The plant includes a hopper, crusher, coal storage bunker of 10000 tonne capacity and 1.6 km long conveyor belt, with the help of which coal will be transferred to railway wagons through Silo bunker of 1000 tonne storage capacity. The cost of the project of 5 million tonnes per annum capacity is Rs. 322 crore. With the commencement of this project, the current rake loading time will be reduced from 5 hours to 1 hour, which will speed up coal dispatch and increase the availability of rakes.

Karo Coal Handling Plant : The plant includes a hopper, crusher, coal storage bunker of 15000 tonne capacity and 1 km long conveyor belt, with the help of which coal will be transferred to railway wagons through silo bunker of 4000 tonne storage capacity. The cost of this project of 7 million tonnes per annum capacity is Rs. 410 crores. With the start of this project, the current rake loading time will be reduced from 5 hours to 1 hour which will speed up the dispatch of coal.

These closed-loop, fully mechanized systems will bring speed and efficiency in the dispatch of coal by eliminating transportation by road and thus reduce diesel consumption. It will also help in reducing dust and vehicle-borne pollution in the area.