Medical colleges rise from 387 to over 800: Patel (See 'Corp Brief') A & C - High Court erred in holding that petitions filed u/s 34 of the Act were barred by limitation, considering that applications were filed well within statutory limitation period: SC (See 'Legal Desk') ICAT marks 20 Years of Excellence with PM e-Drive Dialogue with the industry (See 'Corp Brief') TradeMarks - When special law like Trade Marks Act restricts institution of suits to courts not inferior to District Judge, it remains entirely consistent with Commercial Courts Act, provided High Courts designate District Judges as commercial courts - case referred to Larger Bench: SC (See 'Legal Desk') From Rural Needs to Real-World Solutions: RuTAG 2.0 focuses on deepening Technology Impact (See 'Corp Brief') India International Water Week 2026 concludes with Focus on Climate-Resilient Management (See 'Corp Brief') A&C - Period of limitation u/s 34(3) of Arbitration Act must be reckoned from date of disposal of Sec 33 application, regardless of whether such application is ultimately found to be frivolous or sham: HC (See 'Legal Desk') Board reviews measures for Trader Welfare and Export Promotion (See 'Corp Brief') IPR - Civil remedy u/s 55 of Copyright Act can be pursued through arbitration as agreed alternative dispute resolution mechanism: HC (See 'Legal Desk') DRI seizes 9.40 kg gold worth Rs. 15 crore at Mumbai airport (See 'Corp Brief') NLMC concludes 3-City Investor Outreach Programme for RINL Land E-Auction (See 'Corp Brief') A&C - If a company is employed as conduit for shielding assets from creditors, Court may look beyond corporate structure, for piercing veil: HC (See 'Legal Desk') MEE-TR 2026 to introduce 'Solid Waste Management' as separate Evaluation Criterion of Tiger Reserves (See 'Corp Brief') IPR - If party adopts mark that is deceptively similar to registered mark for identical goods, with full knowledge of prior statutory and common law rights, such adoption constitutes infringement: HC (See 'Legal Desk') Nadda inaugurates Arogya Manthan 2026, marking 8 years of AB PM-JAY (See 'Corp Brief') IPR - Requiring plaintiff to sue at place of its subordinate office because cause of action has arisen there would amount to re-writing Sec 134 of Trade Marks Act: HC (See 'Legal Desk') Union Minister inaugurates Seva First Innovation Challenge at IISc Bengaluru (See 'Corp Brief') Companies Act - Admission of winding-up petition, appointment of provisional liquidator or liquidator, or possession of assets by liquidator does not, by itself, establish irreversibility thereof: HC (See 'Legal Desk') Bharat CPSEs' Consultative Conclave inaugurated at Gati Shakti Vishwavidyalaya (See 'Corp Brief') Competition - Formulation of technical specifications & procurement requirements falls primarily within domain of procuring entities, which are at liberty to set terms suited to their needs - no case of contravention of Sections 3 or 4 is made out: CCI (See 'Legal Desk') SAIL's 54th AGM highlights strong value added steel growth (See 'Corp Brief') An unsuccessful 'success fee' litigation (See CORP EINSICHT)

Railways follows roadmap for supplying rakes for coal

Published: Jan 25, 2022

By TIOLCorplaws News Service

NEW DELHI, JAN 25, 2022: SOME media reports have raised concerns that power generation stations located far from mines are suffering due to discrimination in allotment of rakes. These reports have claimed that the power plant operated by Rattan India Power Ltd in Maharashtra has also been shut down due to coal shortage resulting from insufficient rake allotment by south east central zone of the railways (SECR). Dismissing these misleading media reports, Ministry of Railways has issued a clarification which states that:

1. In South East central railways, there are large number of Thermal power plants which are having less coal stock as per new coal stocking norms. Many of these shorter distance plants have both mechanized unloading flexibility namely ‘Tippler unloading system' which uses Open wagon with side door (BOXN type) and ‘Hopper unloading System' which uses hopper wagon with bottom opening (BOBRN type).

2. The unloading time of hopper rake is much less i:e 3 hours per rake therefore has better turn around. As a result rake supply to these shorter distance plants dealing with faster circuit Hopper rake naturally improves.

3. The Amravati Power plant does not have hopper unloading system. This being the main reason for less supply of rakes.

4. Many of the long distance thermal power plants (TPS) have regulated coal supply during April-June 21-22 to save on the inventory cost. Large no of railway rakes got stabled on account of regulation of coal supply by these long distance TPS. With power demand picking up its existing stock got liquidated.

5. Railways in consultation with MOC & MoP are already having a road map in place for supplying rakes to long distance TPS which is being implemented to build adequate coal stock at these TPS.