Vaishnaw highlights ISM 2.0, indigenous design, manufacturing, talent and India's emergence (See 'Corp Brief') IBC - Arrangement of funds to enable corporate debtor to clear its liabilities, coupled with transfer of funds from cooperative bank loan account of applicant directly to bank, is not valid loan disbursement under IBC: NCLT (See 'Legal Desk') SEBI - SEBI, acting as statutory market regulator, is duty-bound to issue a reasoned, speaking order when a decision carries serious civil consequences for acquirer, target company & investors: SAT (See 'Legal Desk') An unsuccessful 'success fee' litigation (See CORP EINSICHT) Centre commemorates World Patient Safety Day 2026 at NIHFW (See 'Corp Brief') BIMSTEC Energy Centre organises 5-Day Capacity Building Programme (See 'Corp Brief') Scindia inaugurates Renovated Guna Head Post Office in MP (See 'Corp Brief') SEBI - Where material on record discloses need for deeper scrutiny, re-appreciation, review or reconsideration of evidence, leave ought to be granted & the appeal should thereafter be decided on merits: HC (See 'Legal Desk') CCI nod for acquisition of equity of Great White Global by ISAF III Onshore Fund (See 'Corp Brief') From Ink and Ledger to Cloud and Cipher: The Bankers' Books Evidence Act, 2026 - A Critical Appraisal of India's Digital Evidentiary Revolution (See CORP EINSICHT) A&C Act - Question whether particular claim is covered by, or falls outside excepted matters clause of works contract is matter squarely within competence of Arbitral Tribunal u/s 16 of Arbitration and Conciliation Act: SC (See 'Legal Desk') CCI approves acquisition of addl share in Azure Power Global by OMERS Infra (See 'Corp Brief') Beneficiaries express confidence in government policies for e-mobility (See 'Corp Brief') Competition Act - Regulatory decisions taken in exercise of statutory powers not subject to review by CCI; authority concerned is not amenable to scrutiny u/s 4 of Competition Act: CCI (See 'Legal Desk') Semicon 2.0 mission to focus semiconductor design & fabrication; to create 1 lakh jobs (See 'Corp Brief') NLMC to host investor meets ahead of RINL land e-auction (See 'Corp Brief') SEBI - Penalty order under SEBI (PFUTP) Regulations unsustainable where foundational findings regarding volume of manually deleted orders & manipulative intent are perverse & contrary to the record: SAT (See 'Legal Desk') Govt reviews Use of Steel from Ship Recycling to Boost Steel Manufacturing (See 'Corp Brief') Inaugural PDUNASS–GNLU Executive Program on Labour Law concludes at Gandhinagar (See 'Corp Brief') Capital Market - Release of escrow amount maintained for buyback does not bar separate inquiry into alleged fraud under PFUTP Regulations: SC (See 'Legal Desk')

Railways follows roadmap for supplying rakes for coal

Published: Jan 25, 2022

By TIOLCorplaws News Service

NEW DELHI, JAN 25, 2022: SOME media reports have raised concerns that power generation stations located far from mines are suffering due to discrimination in allotment of rakes. These reports have claimed that the power plant operated by Rattan India Power Ltd in Maharashtra has also been shut down due to coal shortage resulting from insufficient rake allotment by south east central zone of the railways (SECR). Dismissing these misleading media reports, Ministry of Railways has issued a clarification which states that:

1. In South East central railways, there are large number of Thermal power plants which are having less coal stock as per new coal stocking norms. Many of these shorter distance plants have both mechanized unloading flexibility namely ‘Tippler unloading system' which uses Open wagon with side door (BOXN type) and ‘Hopper unloading System' which uses hopper wagon with bottom opening (BOBRN type).

2. The unloading time of hopper rake is much less i:e 3 hours per rake therefore has better turn around. As a result rake supply to these shorter distance plants dealing with faster circuit Hopper rake naturally improves.

3. The Amravati Power plant does not have hopper unloading system. This being the main reason for less supply of rakes.

4. Many of the long distance thermal power plants (TPS) have regulated coal supply during April-June 21-22 to save on the inventory cost. Large no of railway rakes got stabled on account of regulation of coal supply by these long distance TPS. With power demand picking up its existing stock got liquidated.

5. Railways in consultation with MOC & MoP are already having a road map in place for supplying rakes to long distance TPS which is being implemented to build adequate coal stock at these TPS.