Principal Scientific Adviser chairs meeting to discuss Biomass Cultivation (See 'Corp Brief') SAFEMA - Appellant have furnished evidence which show satisfactorily that they took all reasonable steps to realise export proceeds : Tribunal (See 'Legal Desk') Companies Act - Winding up petition can be dismissed when contentions raised by parties constitute triable issues as Company Court cannot enter into adjudication of disputed facts of amount due and payable : HC (See 'Legal Desk') Competition Act - In absence of any apparent anti-competitive conduct, decision of purchase or sale of product and quantity thereof is driven by commercial considerations of market players : CCI (See 'Legal Desk') Slum Rehabilitation Act - Preferential right to owner is available only when someone other than owner is being preferred and owner has never before been given or availed of right to develop : HC (See 'Legal Desk') India Pavilion at World Hydrogen Summit showcases Green Hydrogen Mission (See 'Corp Brief') CPC - Application can be dismissed as Intervener has already initiated its own remedy by way of independent Execution Petition : HC (See 'Legal Desk') SEBI Act - Appellant has not shown sufficient cause for condonation of delay in filing appeal : SAT (See 'Legal Desk') PMLA - When questions relating to legality of arrest is under consideration, more holistic and libertarian view is to release Chief Minister of Delhi on interim bail for Lok Sabha General Elections : SC (See 'Legal Desk') Smugglers and Foreign Exchange Manipulators (Forfeiture of Property) Act, 1976 - Order for forfeiture of properties is rightly made as property is occupied through lllegal earning : Tribunal (See 'Legal Desk') Summer Power demand expected to be adequately met during both day and night (See 'Corp Brief') Arbitration Act - As petitioner is not notified as 'financial institution' or 'bank' under RDB Act, there is no bar on parallel proceedings to co-exist under A&C Act as well as SARFAESI Act : HC (See 'Legal Desk') Cr.P.C. - Once order issuing process has been set aside, then applicant has no right to file application u/s 482 of Cr.P.C. for quashment of complaint case : HC (See 'Legal Desk') Competition Act - WordPress.org is justified in taking appropriate action against any developer found non-compliant with prescribed standards and regulations : CCI (See 'Legal Desk') Ministry of Skill signs MoU with Mahindra Ltd to conduct two Pilot Projects (See 'Corp Brief')

NTPC develops infra at Rihand to cart fly ash to cement plants

Published: Aug 17, 2020

By TIOL News Service

NEW DELHI, AUG 17, 2020: NTPC has developed an infrastructure at Rihand project in Uttar Pradesh to transport fly ash in bulk to cement plants, located at distance, at a cheaper cost. The development is in line with NTPC's commitment towards 100 percent utilization of fly ash from power plants.

As per a statement issued by NTPC Ltd., the first rake of 59 BOXN type of railway wagons carrying 3450 Metric Tonne (MT) of fly ash was flagged off from NTPC’s Rihand Super Thermal Power station by Shri Balaji Iyengar, Executive Director (NTPC Rihand) for ACC Cement Manufacturing Plant, Tikaria, U.P. located at a distance of 458 kms, in presence of other senior officials of NTPC Rihand.

Mr Lalit Trivedi, General Manager, East Central Railway and Mr Suresh Rathi, Head Supply Chain, ACC along with his team joined the occasion through video conferencing. To transfer the first tranche, officials from NTPC Rihand approached East Central Railway along with leading cement producers to commence the supply of fly ash in BOXN wagons covered with tarpaulin. The innovation will pave the way for efficient and safer transportation of fly ash from the power plants to cement production units located at a distance in larger quantity.

The effort marks the beginning of a new era for the transportation of fly ash from a remote location to a consumption centre, enabling power plants for upgrading the utilization of fly ash with the availability of additional material loading avenues for Indian Railways and accessibility of fly ash to the cement plants in an environment-friendly manner at a competitive price. During the financial year 2019-20, almost 44.33 million tonnes of fly ash was utilized for various productive purposes, being 73.31% of the ash generated.

Moreover, company is looking at new avenues of fly ash management like fly ash based geo-polymer road, use of bottom ash as replacement of fine aggregate (sand) in cement concrete. Also, NTPC has plans to set up fly ash classifier unit for export purposes.

With a total installed capacity of 62.9 GW, NTPC Group has 70 Power stations comprising of 24 Coal, 7 combined cycle Gas/Liquid Fuel, 1 Hydro, 13 Renewables along with 25 Subsidiary & JV Power Stations. The group has over 20 GW of capacity under construction, including 5 GW of renewable energy projects.